The following short description gives the working procedure in outline. It can in certain details be modified when required.
Step 1. The tank bottom – plates are placed on the prepared foundation and welded together.
Step 2. The beams or lattice work of the roof are assembled and finally joined to the upper rim of the shell ring.
Step 3. The jacking equipment is installed in the tank. The plates of the second shell ring (next to the top ring) are positioned outside the first one.
Step 4. The completed part of the tank (roof and top shell ring) is lifted hydraulically to a height at which the plates of the second ring can be moved into place and the roof sheeting can be completed.
Step 5. The plates of the second shell ring are located exactly and welded together to the lower edge of the first ring.
Step 6. The plates of the third shell ring are placed outside the second shell ring.
Step 7. The completed part of the tank (roof the two uppermost shell rings) is lifted.
Step 8. The above cycle of operations is repeated until the last (bottom) shell ring is finished.
Step 9. The entire tank is lowered down to the bottom plate and welded to this.
Step 10. The lifting equipment is dismantled.
The tank construction process needs two kinds of equipment, respectively is the welding machine and the hydraulic jacking system, the welding machine is divided into the horizontal welding machine and the vertical welding machine;the hydraulic jacking system is also divided into senior hydraulic jacking system and simple hydraulic jacking system.(If your tank is bottom to top,you don’t need the hydraulic jacking system.)
In recent years, we have received a lot of customer demand, they want to have a special hydraulic roof for lifting granaries and enamel tanks.
WINCOO IUCs are not just manufactured; they are meticulously engineered based on decades of field experience. We understand the real-world challenges you face, and our design philosophy focuses on delivering tangible benefits where it matters most.
In the world of long-distance pipeline construction, every single weld is a critical point of integrity. The alignment of pipe joints before welding is a fundamental step that dictates the quality, safety, and longevity of the entire pipeline system.
Seeking a durable, safe, and cost-effective heating solution for your pipelines? Our robust Medium Frequency Induction Heaters are built for the field, ensuring project continuity and long-term savings.
Boost efficiency, ensure superior weld quality, and cut costs on your pipeline projects. Discover how our Medium Frequency Induction Heaters are the ideal solution for pipeline pre-heating, post-weld heat treatment, and drying.
Sign up for our newsletter to receive the latest news.
Copyright © 2020 WINCOO ENGINEERING CO.,LTD
Support By:Leadong