At present, there are six construction methods of large storage tank construction: hydraulic jack, central column, floating, forward loading, mechanical jacking.Hydraulic jacking system is the most widely used one, which is characterized by wide adaptability and can theoretically be applied to any size tank;The operation control is simple, reliable and less threatening.So it is adopted by more and more people.Hydraulic jack is an important part of hydraulic jacking system.
Here is the content list:
What are the product components of the hydraulic jack?
What are the characteristics and applications of hydraulic jack?
What are the construction steps of hydraulic jack?
What are the product components of the hydraulic jack?
One Module include
1 set x Power Pump Station: Hydraulic power supply, motor power 4KW, rated flow is about 15l/min.
5 sets x jacking cylinder: 25 tons rated (18 tons, 100%) (Including Hydraulic Jacking Device Components — Steel Cables, Support Device, Pull Rod, etc.)
5 sets x oil hoses system:One tank construction needs one jacking control system. Each jacking control system includes:
1 set x Electrical Controls and operating panels:
Each set includes:
1 centralized PLC operation control box,
1 power source cabinet(With the concentrated push-button and automatic PLC control system or single-set handle operated control.)
What are the characteristics and applications of hydraulic jack?
Application
1.The hydraulic jack are mainly used for vertical tank top to bottom construction;
2.Also it can be used for mega work piece jacking or lifting.
Features
1.The hydraulic jacking system consists of hydraulic pump station, cylinders, steel wire, and strokes. Easy to installation and operation;
2.The hydraulic jacking system utilizes PLC central control to handle lift. Each power pack is equipped with auxiliary balance device to guarantee the precision of simultaneously lifting;
3.Hydraulic jack pump station has subsidiary manual control and central control two operation models. The cylinder can be adjusted to lift separately or to lift with several others as one group, and multi groups can also be integrated to lift reach better precision and better welding effect;
4.All the cylinders are with safety valve. It can be automatically locked to avoid cylinder/ tank dropping even under situation of power off, high-pressure hose broken, burst;
5.The cylinder is with one high pressure hose to avoid oil leaking that usually happen by the traditional multiple hoses. Cylinder will return to initial condition by itself weight;
6.Stroke of Hydraulic cylinder is 1475mm, which can satisfy each annular shell with 2500 plate one-step lift. Greatly reduce the time waste;
7.Hydraulic cylinder basic height is 2050mm, which can match automatic girth welding machine to proceed internal girth seam welding;
8.Module configuration, the hydraulic jack quantity can be adjusted as per different size of tank and weight
9.High efficiency, each time lifting or falling down only needs around 15 minutes;
10.Can well cooperate with our tank welding machines, which can greatly reduce the manpower cost and reduce the construction time; Usually one Horizontal seam welding machine can match 6-10 skilled welder. Vertical seam welding machine can match around 20-30 people skilled welder and butt/fillet welding tractor can match 6-15 skilled welder.
What are the construction steps of hydraulic jack?
The following short description gives the working procedure in outline. It can in certain details be modified when required.
1.The tank bottom – plates are placed on the prepared foundation and welded together.
2.The beams or lattice work of the roof are assembled and finally joined to the upper rim of the shell ring.
3.The hydraulic jacking system is installed in the tank. The plates of the second shell ring (next to the top ring) are positioned outside the first one.
4.The completed part of the tank (roof and top shell ring) is lifted hydraulically to a height at which the plates of the second ring can be moved into place and the roof sheeting can be completed.
5.The plates of the second shell ring are located exactly and welded together to the lower edge of the first ring.
6.The plates of the third shell ring are placed outside the second shell ring.
7.The completed part of the tank (roof the two uppermost shell rings) is lifted.
8.The above cycle of operations is repeated until the last (bottom) shell ring is finished.
9.The entire tank is lowered down to the bottom plate and welded to this.
10.The lifting equipment is dismantled.
Hydraulic jack is mainly used in large tank construction. WINCOO ENGINEERING CO.,LTD is supplying tank hydraulic jack equipment to tank contractors worldwide.
The working principle of the rolling machine is to make the work roll move through the action of hydraulic pressure, mechanical force and other external forces, so that the sheet is bent or rolled into shape.
What are the operating taboos of the rolling machine?
How to operate the rolling machine safely and correctly?
What are the inspection measures for rolling machine?
1. When multiple people work together on the rolling machine, there must be a special person to command.
2. It is strictly forbidden to overload the rolling machine.
3. The tilting and resetting of the lifting and turning bearing of the upper roller and the balance of the upper roller must be carried out after the main drive is stopped.
4. It is forbidden to pile up workpieces and sundries in the workplace, and keep the machine tool and the site clean at all times.
5. After the operation of the rolling machine is completed, the power supply should be cut off and the power box should be locked.
The first is that the operator should organize the surrounding environment of the operation before operating the rolling machine to maintain a good operating environment. At the same time, the operator must be neatly dressed to avoid pulling the corners of clothes into the roller during the operation. In the process of work, it must be noted that the operator can only stand on both sides of the workpiece, which is the most reasonable position. If you want to adjust and measure the roundness during the operation, you must stop the operation, and it is forbidden to operate during the operation. A certain margin should be left at the end of the processing part.
1. During the running process, if the rolling machine has irregular noise, impact and other abnormal phenomena, it should be stopped immediately for inspection.
2. During the operation, all personnel should coordinate with each other, obey the command of the person in charge of the rolling plate, and it is forbidden to start the machine without a password.
3. When operating the rolling machine, pay great attention to the fact that the hand is pressed by the steel plate and rolled in together with the steel plate.
4. Be careful not to collide with the machine when lifting the steel plate or reel with a crane. After the coiling is finished, make sure that all materials are finished and the site is cleared, and the maintenance of the equipment is done well, and the power is turned off in time.
Based on clients’ facility/site space availability, WINCOO ENGINEERING CO., LTD is able to study/design and present matched configurations on project schedule, quality, cost and productivity to guarantee production pace in accordance with project requirement. They are committed to providing various rolling machines of high quality for all customers from all over the world.
The use of tank welding machine requires a series of processes from raw materials to finished products. The completion of these processes requires corresponding various tank welding machines and welding, electrical control, and detection devices. These devices and devices are available in various types according to different process requirements.
Why do we choose tank welding machine?
What are the steps for using the tank welding machine?
What is the workflow of tank welding machine?
(1) Tank welding machine can reduce the heat input to the minimum required amount, the metallographic change range of the heat affected zone is small, and the deformation caused by heat conduction is also the lowest.
(2) The welding process parameters of 32mm plate thickness single-pass welding have been verified and qualified, which can reduce the time required for thick plate welding and even save the use of filler metal.
(3) Tank welding machine does not need to use electrodes, and there is no concern about electrode contamination or damage. And because it does not belong to the contact welding process, the wear and deformation of the equipment can be minimized.
(4) The laser beam generated by the tank welding machine is easy to focus, align and be guided by optical instruments. It can be placed at an appropriate distance from the workpiece, and can be re-guided between tools or obstacles around the workpiece. Unable to play due to the space constraints mentioned above.
(5) The workpiece of the tank welding machine can be placed in a closed space (evacuated or the internal gas environment is under control).
Raw material (strip coil) - feeding - shearing butt welding (manual welding) - storage bin - feeding forming - high frequency welding - deburring - cooling water jacket - sizing and straightening - flying saw cutting - blanking (manual stacking and dressing)
Tank welding machine refers to an automatic welding machine that performs transverse welding of large tanks. At present, according to the requirements of the tank structure and construction process, a forward and reverse dual-purpose transverse seam automatic welding machine has been developed and produced. The complete set of equipment consists of welding walking frame. It consists of submerged arc automatic welding system, flux recycling system and holding system, operation box and power distribution cabinet. The welding system is equipped with a multi-functional welding system to ensure that the quality of its products is well guaranteed. The welding system with excellent performance in tank welding machine is a reliable guarantee for welding quality and construction progress. Considering the use environment of the construction site, tank welding machine adopts a special welding system for automatic welding of tank construction, which can work in various harsh environments, effectively ensure the stability of the machine running.
Based on clients’ facility space availability, WINCOO ENGINEERING CO., LTD is able to study/design and present matched configurations on project schedule, quality, cost and productivity to guarantee production pace in accordance with project requirement.
We currently have three types of tank jacking system, which are advanced tank jacking system, chain tank jacking system and simple tank jacking system.Advanced tank jacking system has the most advanced hydraulic jacking technology available.Today we talk about the advanced tank jacking system.
Here is the content list:
What is the working principle of advanced tank jacking system?
What are the product components of the advanced tank jacking system?
What are the construction steps of advanced tank jacking system?
Advanced tank jacking system (package unit) is evenly distributed around tank inner wall. Tank top and upper (the first layer) wall plates are lifted first and then install and weld wall plates of tank body. Self locking advanced tank jacking system and hydraulic hoist composing of lifting frame and lifting rod are adopted. When oil enters advanced tank jacking system, upper clamp fastens and lifts lifting rod and expansion ring and mobilize tank (including tank top) to ascend upward. When oil returns to jack, upper clamp returns with piston and lower clamp automatically fastens lifting rod without gliding. The jack repeats the movement and make lifting rod ascend with tank to designated height (spare height for next layer of plate). After butt weld of next layer of wall plates, open upper and lower loosening device and loosen upper and lower clamp to make lifting rod and expansion ring descend to lower expanded and welded rib plate of the next layer of wall plates and then lift. Repeat the process and ascend welded tan till the last layer of wall plates are installed and welded. The installation of the whole storage tank is completed.
1.One Module include
2.1 set x Power Pump Station: Hydraulic power supply, motor power 4KW, rated flow is about 15l/min.
3.5 sets x jacking cylinder: 25 tons rated (18 tons, 100%) (Including Hydraulic Jacking Device Components — Steel Cables, Support Device, Pull Rod, etc.)
4.5 sets x oil hoses system:One tank construction needs one jacking control system. Each jacking control system includes:
5.1 set x Electrical Controls and operating panels:
1.1 centralized PLC operation control box,
2.1 power source cabinet
With the concentrated push-button and automatic PLC control system or single-set handle operated control.
Motor and PLC are with brand of SIMENS
Main electric element are Schneider brand
Hose with USA and China JV famous brand
The following short description gives the working procedure in outline. It can in certain details be modified when required.
1.The tank bottom – plates are placed on the prepared foundation and welded together.
2.The beams or lattice work of the roof are assembled and finally joined to the upper rim of the shell ring.
3.The hydraulic jacking system is installed in the tank. The plates of the second shell ring (next to the top ring) are positioned outside the first one.
4.The completed part of the tank (roof and top shell ring) is lifted hydraulically to a height at which the plates of the second ring can be moved into place and the roof sheeting can be completed.
5.The plates of the second shell ring are located exactly and welded together to the lower edge of the first ring.
6.The plates of the third shell ring are placed outside the second shell ring.
7.The completed part of the tank (roof the two uppermost shell rings) is lifted.
8.The above cycle of operations is repeated until the last (bottom) shell ring is finished.
9.The entire tank is lowered down to the bottom plate and welded to this.
10.The lifting equipment is dismantled.
Above we talked about the working principle of advanced tank jacking system,equipment components and installation steps.If you need to know more, please visit our website for more information about advanced tank jacking system.